Farmland and Timberland Updates:
- March 2021 – Farmland and Timberland will have access to the test submission environment; Both committees will submit Q4 data into the new system using the new template
- Template completed by Manager: February 28th
- Submission Training: Week of March 7th
- Portal open to managers for testing: March 7th
- Completion of Q4 upload in test portal: March 14th
- Completion of Q1 upload in test portal: End of June
- July 20th/25th - Users submit Q2 data to current system
- October 20th/25th - Users submit Q3 data to current system
- Portal reopens to managers for testing Q3 data: Mid-November
- NCREIF will assess next steps on go-live launch dates and parallel testing schedule for Q4
Commercial Property and Fund Updates:
- November 2021 - Templates released and review webinars scheduled
- August 2022 - Begin collection of new subtype data fields in a separate supplemental collection.
- September 8th 2022 - Returned subtype data to NCREIF
- October 20th/25th - Users submit Q3 data to current system for commercial and open-end fund
- October/November 2022 - NCREIF releases supplemental Subtype data with Q3 data
- Training for new Submission Portal will begin mid-2023